The rebuilt Trinitie/Juniper Trail Bridge is open to all traffic!!! You may freely travel on it.
Construction of the bridge replacement took 199 days, instead of the 211 days forecasted, according to an announcement released today by the Town, which had earlier this month announced that the bridge would reopen by Memorial Day.
The road was closed on Dec. 9, 2024 for the extensive multi-million-dollar project, which replaced an often-repaired culvert with a new core slab bridge.
The construction contract awarded to Smith, Rowe LLC of Mt. Airy is expected to come in at or below the authorized $1,667,178.70 cost, the Town said.
Kimberley-Horn and Associates, Inc., of Raleigh designed and engineered the bridge.